Native Restoration Planting Update: September 13, 2023
/Native Restoration Planting Update as of September 13, 2023.
Read MoreNative Restoration Planting Update as of September 13, 2023.
Read MoreAUI survey crews will be onsite Thursday, October 13, 2022, in the Upper Canyon area of Ruidoso. Their work will be limited to the area along the river adjacent to 623 Main Rd at the corner of Main Rd and Fox Dr. Additionally, on Wednesday, October 19, and Thursday, October 20, project personnel will be visiting project areas to conduct site assessments.
Read MoreAUI Inc. will begin construction on the Hazard Mitigation project in the Location 8A area on October 3, 2022. This work includes reconstructing the existing 8” sanitary sewer line from 121 Singing Pine Rd to 113 Singing Pine Rd. As part of the sewer line replacement and protection, AUI will construct a floodwall along the length and encase the new sewer line in concrete. As part of the reconstruction, the existing concrete encased manhole near 121 Singing Pine Rd. will be removed and replaced. Construction at this location is expected to take a bit over eleven (11) weeks to be performed and is anticipated to run from October 3, 2022, to December 20, 2022.
Read MoreConstruction Crews to return to the Sleepy Hollow Lift Station site from 9/26/2022 to 10/7/2022. Lane closures and detours on Sleepy Hollow Road due to construction for Phase 2: Lift Stations Project. Please follow the detour route, traffic control signs, and information, approach the area with caution, at a very slow speed, and watch for personnel. FOR MORE INFORMATION, PLEASE CALL ADAM SANCHEZ AT 575-937-0544 OR MARTY LUNA AT 575-937-0777
Read MoreRUIDOSO, NM – September 16, 2022 – J. Aimone Associates, a subcontractor for AUI Inc., will be performing the required digital video recording for the Village of Ruidoso’s Hazard Mitigation phase in the Upper and Middle Canyon areas beginning Friday, September 23 through Sunday, September 25. Videotaping is required so there is documentation of the condition of residences and properties prior to the beginning of construction and before any trees are removed from the proposed project sites of the mitigation phase of the ongoing FEMA sewer line rehabilitation project. J. Aimone Associates will be on-site to videotape with voice description of the Rio Ruidoso, access routes, and construction limits to document existing utilities, existing drainage patterns, adjacent building structure, landscaping, private yards, gates, fences, and garden walls. The recording will be performed at all 7 project locations. This work will cause little to no disturbance. Before heavy construction begins, AUI Inc. will ensure that additional notification and public outreach will take place.
If you have any questions about the videotaping work, please contact Patti Watson, at 1-800-687-3417, 505-245-3134 direct office, 505-269-9691 cell, and email pattiw@cwastrategic.com.
Survey crews will be working for the Village of Ruidoso to support the construction of the Hazard Mitigation phase in the Upper Canyon area beginning on Monday, August 8, 2022. Current survey work will be limited to the area along the river between 627 Main Road and 828 Main Road.
Read MoreVillage of Ruidoso residents can expect work to continue on the sewer project. Beginning on March 21, 2022, crews from SAK Construction will be performing maintenance on sewer lines within the area of Fern Trail in the Village of Ruidoso. The work will continue through April 27, 2022. This construction is weather dependent and therefore subject to change.
Read MoreSAK will be working in Ruidoso from February 7-12, 2022. They will concentrate at Meander Drive between Paradise Canyon and Reese Drive. The week of February 14-19, the SAK crews will be mobile as they will be retaking videos. Please follow the traffic control signs and all posted information, approach the area with caution, at a very slow speed, and watch for crews.
Read MoreA public meeting is scheduled for January 19, 2022, at 6:00 PM to discuss the Ruidoso Sewer Line Hazard Mitigation and Stabilization Phase. The meeting will be held at Village Hall located at 313 Cree Meadows Drive. A Zoom link is also available for anyone who wishes to attend virtually.
Read MoreLane closures and detours on Sleepy Hollow Road and the southern portion of Mechem Drive near Sudderth Drive due to construction for Phase 2: Lift Stations Project Please follow the detour route, traffic control signs, and approach the area with caution, at a very slow speed, and watch for personnel.
Read MorePortions of Main Road, at the roundabout, near Vision Drive, D Street, and 1st Street will be reduced to one lane due to construction for the Phase 2: Lift Stations Project. Please follow the traffic control signs and approach the area with caution, at a very slow speed, and watch for personnel.
Read MorePortions of Main Road, at the roundabout, near Vision Drive, D Street, and 1st Street will be reduced to one lane due to construction for the Phase 2: Lift Stations Project. Please follow the traffic control signs and all posted information, approach the area with caution, at a very slow speed, and watch for crews.
Read MoreThe week of September 15, Smithco Construction began construction on Lift Stations Phase 2. Please note construction will occur at properties along Sleepy Hollow Road and at 2932 Sudderth Road, but will not result in any street closures. Expect work crews on-site between 7:00 am – 5:30 pm, Monday thru Thursday.
Read MoreThe week of August 30 - September 3, 2021, MP Chavez will continue working on the pipe construction located at the intersection of River Trail and Country Club. Tuesday and Wednesday, September 7-8, we will be working on the point of repair located at 103 North Loop. Please look for signs indicating which road and lane will be closed. Approach the area with caution, at a very slow speed, and watch for employees directing traffic.
Read MoreBeginning August 16 through August 19 from 6:00 pm to 12:00 am, the Village of Ruidoso will be performing maintenance on the main sewer lines on Mechem Drive from the turnoff to Alpine Village to Sudderth Drive. The road will be one lane throughout Mechem Drive at different areas where the maintenance will be performed (manholes).
Read MoreDue to rain, we are running a day behind. MP Chavez won't be able to get back to the construction site at Country Club and River Trail until Friday, 7/29/2021. Construction on this site will extend until 8/12/2021.
Read MoreBeginning July 27, 2021, crews from MP Chavez will be working on River Trail between Country Club Drive and River Trail on new construction until their anticipated completion on August 6. Please look for signs indicating which road and lane will be closed. Approach the area with caution, at a very slow speed, and watch for employees directing traffic.
Read MoreSAK crews will be installing top hats at Meander Dr, 200 yards East from Paradise Canyon Dr. the week of July 12. There will be no traffic disruptions. We will continue to keep you posted.
Read MoreThe lining crew has finished installing completely, and they will be demobilizing at the end of May. The week of June 1 to June 5 there will be no one from SAK or the manhole crew working locally. The week of June 7 to June 12, the Top Hat crew that seals the liners, as well as the manhole crew, will resume their work schedule. We will continue to keep you posted.
Read MoreBeginning May 18 at 8:00 a.m., the Village of Ruidoso will be repairing a sewer line on Burro Lane which will be closed. The 2800 block of Sudderth Drive will have one lane closed on the outside eastbound side of Burro Lane. The road and lane closures will continue through May 20 or until the work has been completed.
Read MoreThe Ruidoso Sewer Project is a FEMA-funded project that will improve the existing sewer lines from the Upper Canyon in Ruidoso, New Mexico, to the Waste Water Plant.
Construction update for Phase 3 – Hazard Mitigation and Stabilization Project as of May 3, 2024.
Native Restoration Planting Update as of September 13, 2023.