The design of the six Hazard Mitigation sites has been completed. The Village of Ruidoso is acquiring easements from affected property owners.
Current Activities
Easement Acquisition: July 2021 to March 2022.
Resource Sheet: The value and use of native vegetation to control streambank erosion.
The work at locations 16a, 5b, 5c, and 8a has been completed with replanting. Location 9 has some additional work to protect the manhole, and the subcontractor will be on site for replanting. Location 18a will also have some replanting. Pole planting and reseeding will take place next year.